Wisconsin roofing: permits, codes and approvals

Wisconsin's Uniform Dwelling Code, city re-roof permits, the DSPS Dwelling Contractor credential needed to pull permits, the insurance-claim roofing law, ATCP 110 contract rules and construction lien notices.

1 · Product approvals

Product approvals

Wisconsin has no state roofing product approval or listing system for homes. Local inspectors rely on the dwelling code's requirements, manufacturer instructions and recognized evaluation reports.

2 · Permit forms

City re-roof permits

There is no single statewide re-roof permit rule. Each city decides, and the answer ranges from always (Madison) to only for 3+ unit or historic buildings (Green Bay).

3 · Code rules

Code rules

One- and two-family homes fall under the Wisconsin Uniform Dwelling Code (Wis. Admin. Code SPS 320-325). Roof weather protection is covered in SPS 321.28. Official adoption page ↗

4 · Wind, fire and storm programs

Wind, fire and storm programs

No state FORTIFIED grant or roof-discount mandate was found. Wisconsin's main storm-related rule is its insurance-claim roofing law, which bans deductible rebates and lets homeowners cancel after a claim denial.

5 · License and insurance

License and insurance

Wisconsin has no roofing-specific license. To pull a building permit on a one- or two-family home, a contractor needs a DSPS Dwelling Contractor credential and must hold or employ a Dwelling Contractor Qualifier. Owner-occupants are exempt.

6 · Lien and contract forms

Lien and contract rules

Wisconsin roofers must give a lien notice in the contract, a lien-waiver notice before signing, and written contracts when taking deposits. Lien claims are due within 6 months of last work.

Prime contractor lien notice (Wis. Stat. 779.02(2))A prime contractor who uses subs or suppliers must put the statutory notice in the written contract (8-point bold), or serve it within 10 days after first work. This applies to homes with 4 or fewer units.Sub and supplier notice: 60 daysA subcontractor or supplier has lien rights only if it serves the owner written notice within 60 days after first furnishing labor or materials.Lien claim: 30-day notice, then 6 months (Wis. Stat. 779.06)Serve the owner a written notice of intent at least 30 days before filing. File the lien claim within 6 months after your last work, and start suit within 2 years after filing.Lien waiver notice (ATCP 110.025)Before the contract is signed, give the homeowner the separate 'Notice of Consumer's Right to Receive Lien Waivers' and keep proof they got it. If they ask, provide waivers from all subs and suppliers before final payment.Written contract rules (ATCP 110.05)A written, signed contract is required if you take any payment before finishing or solicit away from your business. It must list materials (brand and grade), price, and start and finish dates, and the buyer gets a copy before work or payment.Insurance-claim cancel right (Wis. Stat. 100.65)Before signing, ask in bold type whether the job is tied to an insurance claim and attach a Notice of Cancellation. The homeowner may cancel by the end of the 3rd business day after a written claim denial, and payments must be refunded within 10 days.

Install instructions by brand: all makers →

Public records, last checked Oct 23, 2026. Always verify on the official source before you permit.